To achieve these results, the project has a number of Actions to meet:

A. Preparatory actions, elaboration of management plans and/or of action plans

  • ACTION A.1. Prepare civil engineering drawings for fish passage improvements
  • ACTION A.2. Secure permissions and consents for fish pass construction
  • ACTION A.3. Prepare Communications Plan

B. Purchase/lease of land and/or compensation payments for use rights

  • ACTION B.1. Purchase of and One-off compensation for temporary access to land

C. Concrete conservation actions

  • ACTION C.1. Provide Alosa fallax migration to historic spawning grounds on the River Severn
  • ACTION C.2. Provide Alosa fallax migration to historic spawning grounds on the River Teme
  • ACTION C.3. Review the scientific and legal rationale for the designation of the spawning areas as new Special Areas of Conservation on the River Severn and River Teme.

D. Monitoring of the impact of the project actions

  • ACTION D.1. Undertake scientific monitoring for Alosa fallax
  • ACTION D.2. Assessment of the socio-economic impacts
  • ACTION D.3. Assessment of the impacts on ecosystem function

E. Public awareness and dissemination of results 

  • ACTION E.1. Public and stakeholder awareness raising and dissemination of results
  • ACTION E.2. Technical dissemination and transfer of results

F. Project management

  • ACTION F.1. Project Management
  • ACTION F.2. Produce After-LIFE Conservation Plan
  • ACTION F.3. Monitor project performance indicators